Civil & Infrastructure
Industrial Estate Internal Road Development
Full internal road package inside an operating manufacturing premises — carriageway, kerb, footpath and road-side drainage — executed in phases without stopping plant traffic.
Hero photograph
Completed industrial internal road with kerb and footpath, plant buildings alongside, trucks moving normally.
Client
Confidential — Manufacturing Client
Location
Pune, Pune
Year
2024
Duration
Approximately 4 months
The challenge
What the client was up against.
The existing internal road had failed at the gate and weighbridge approach, where loaded trucks stand for extended periods and water pooled every monsoon. The plant could not be closed, and material movement had to continue throughout.
Our approach
What we actually did.
The alignment was surveyed and split into phases, so that one half of the loop was always available to plant traffic. Cement concrete pavement was adopted at the gate and weighbridge approach where standing loads and water made bituminous surfacing a poor choice, with bituminous surfacing on the remaining stretches. Road-side drainage was corrected first so that the new surface drained rather than held water.
Before and after
Drag the divider.
Opening condition on the left, completed work on the right — from the same position, so the comparison is honest.
After
The same stretch rebuilt in cement concrete with corrected drainage and painted kerb.
Before
Failed internal road surface with potholes and standing water at the weighbridge approach before work.
Equipment deployed
What the client got
From site
Execution photographs.
Project photograph 1
Paver laying bituminous surface on the phased loop.
Project photograph 2
Cement concrete panel being poured at the gate approach.
Project photograph 3
Road-side drain being cast before surfacing.