Industrial Estate Internal Road Development

Full internal road package inside an operating manufacturing premises — carriageway, kerb, footpath and road-side drainage — executed in phases without stopping plant traffic.

Client

Confidential — Manufacturing Client

Location

Pune, Pune

Year

2024

Duration

Approximately 4 months

The challenge

What the client was up against.

The existing internal road had failed at the gate and weighbridge approach, where loaded trucks stand for extended periods and water pooled every monsoon. The plant could not be closed, and material movement had to continue throughout.

Our approach

What we actually did.

The alignment was surveyed and split into phases, so that one half of the loop was always available to plant traffic. Cement concrete pavement was adopted at the gate and weighbridge approach where standing loads and water made bituminous surfacing a poor choice, with bituminous surfacing on the remaining stretches. Road-side drainage was corrected first so that the new surface drained rather than held water.

Before and after

Drag the divider.

Opening condition on the left, completed work on the right — from the same position, so the comparison is honest.

BeforeAfter

Equipment deployed

Paver finisher and roller train
Excavators, tippers and graders
Concrete mixers and vibrators
Total station and auto level

What the client got

Plant traffic maintained through the entire construction programme
Field density and material test records compiled into a handover file
Standing-water failure at the weighbridge approach eliminated by design
As-built levels handed over to the client's engineering team

From site

Execution photographs.