HT Transformer Substation Installation & Commissioning

Erection and commissioning of a high-tension transformer substation with associated civil works, protection, earthing and statutory clearance.

Client

Confidential — Industrial Client

Location

Pune, Pune

Year

2023

Duration

Approximately 3 months

The challenge

What the client was up against.

The client needed additional connected load for a new production line, on a compressed timeline, with the civil and electrical scopes historically supplied by two contractors whose programmes never aligned.

Our approach

What we actually did.

MGP executed both scopes. The plinth, oil soak pit and cable trenches were built by our own civil team to the electrical layout, removing the usual handover delay. Transformer placement, switchgear installation, protection wiring and earth mat followed immediately, and pre-commissioning testing was scheduled around the Electrical Inspectorate's inspection calendar rather than after it.

Before and after

Drag the divider.

Opening condition on the left, completed work on the right — from the same position, so the comparison is honest.

BeforeAfter

Equipment deployed

Transformer jacking and handling equipment
Oil filtration and testing plant
Transformer ratio and relay testing kits
Earth resistance testers

What the client got

Civil and electrical scope delivered by one contractor with no interface delay
Earth resistance achieved within the specified limit before charging
Statutory clearance obtained and substation charged under controlled sequence
Complete energisation file handed over with all test records

From site

Execution photographs.

Have a similar requirement?

Send us your site details and scope. We will tell you what it needs, and whether a survey should come before any number is discussed.

Prefer to talk?+91 88308 89392
CallWhatsAppEnquire